The Challenge
Faltec Europe is a world-class manufacturer and an accredited Tier 1 supplier to the automotive sector, based on International Drive in East Boldon, near Sunderland. Automotive manufacturing runs on a steady supply of electricity, and Faltec was keen to do more for the environment while bringing its energy costs down.
It wanted a partner with real attention to detail and clear communication, and a solution that would not tie up capital.
The Solution
Eden Sustainable designed and delivered a 675 kWp rooftop solar PV system on Faltec’s low-pitch steel roof, made up of 1,534 JA Solar panels feeding Solis inverters. It was funded through a Power Purchase Agreement (PPA), so Faltec paid nothing upfront and buys the electricity generated on its own roof at a rate below the grid.
Eden managed the full project, from design to installation and commissioning, with production kept running throughout. Operations and maintenance are included for the full term of the PPA, with Eden responsible for keeping the system performing. The system has been generating since 2025.
The Outcome
The solar now saves Faltec around £65,000 a year on electricity and avoids 119 tonnes of CO₂ annually, with no capital outlay. Over 25 years, that adds up to more than £1.6 million in savings.